Final Project Update: July 1, 2022

 In Project Updates

PLEASE NOTE: This is the FINAL update for the GSP Interchange 145 Improvement Project.

GSP ROADWAY AND INTERCHANGE 145 TOLL PLAZA

  • The Garden State Parkway implemented “One-Way Tolling” at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
  • Northbound Garden State Parkway traffic has been restored to its original alignment with three (3) through lanes, between Milepost 145.9 and Milepost 146.8 (Interchange 145) in East Orange and the addition of a second exit lane into Interchange 145.
  • Southbound Garden State Parkway traffic has been restored to its original alignment with three (3) through lanes, between Milepost 147.3 and Milepost 146.7 (Interchange 145) in East Orange and the addition of a second southbound entrance ramp lane from Interchange 145.
  • All work has been completed.   

REPLACEMENT OF CENTRAL AVENUE OVERPASS

  • All work has been completed.

 

ORATON PARKWAY IMPROVEMENTS

  • All work has been completed.

 

STRUCTURE NO. 144.7: GSP UNDER CLINTON AND SPRINGFIELD AVENUES

  • All work has been completed.

STRUCTURE NO. 146.0: GSP OVER 14TH AVENUE

  • All work has been completed.

STRUCTURE NO. 146.1: GSP OVER SOUTH ORANGE AVENUE

  • All work has been completed.

STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET

  • All work has been completed.

STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)

  • All work complete.