Replace the Central Avenue Bridge to accommodate additional auxiliary lanes on the GSP
Utility upgrades
CONSTRUCTION:
Bridge construction work to be performed in three (3) stages following utility relocations
Temporary traffic shifts will be utilized to facilitate the work
Short duration temporary detours will be needed during utility relocation work
Significant utility relocation work including drainage, water mains, gas mains and electrical facilities will be performed
Utility relocation work to begin on or about November 2018
Location Updates
March 5, 2021
On 03/08/21, a new traffic pattern will be implemented on Central Avenue between Watson Avenue and Hawthorne Place. All travel lanes and turn lanes will be re-opened over the bridge. Eastbound and westbound left turns at Oraton Parkway and Whittlesey Avenue will be restored. Please refer to the new graphic below for details.
During the week of 03/08/21, Central Avenue traffic will be restored to two travel lanes in each direction.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]