Replace the Central Avenue Bridge to accommodate additional auxiliary lanes on the GSP
Utility upgrades
CONSTRUCTION:
Bridge construction work to be performed in three (3) stages following utility relocations
Temporary traffic shifts will be utilized to facilitate the work
Short duration temporary detours will be needed during utility relocation work
Significant utility relocation work including drainage, water mains, gas mains and electrical facilities will be performed
Utility relocation work to begin on or about November 2018
Location Updates
November 16, 2018
Utility-related work will continue at the intersection of Central Avenue near Oraton Parkway and Birchwood Avenue. Minor traffic impacts are expected. Work will be supported by East Orange Police.
On Monday, 11/19/18, a new work zone will be created on the south side of Central Avenue Bridge over the GSP. Two Central Avenue travel lanes will be maintained westbound and one travel lane will be maintained eastbound over the bridge. Please refer to the graphic below and CLICK HERE to see full-sized, animated graphics of the detours on the project website.
November 9, 2018
Utility-related work will continue at the intersection of Central Avenue near Oraton Parkway and Birchwood Avenue. Minor traffic impacts are expected. Work will be supported by East Orange Police.
During the week of 11/12/18, a new work zone will be created on the south side of Central Avenue Bridge over the GSP. Two Central Avenue travel lanes will be maintained westbound and one travel lane will be maintained eastbound over the bridge. Please CLICK HERE to see full-sized, animated graphics of the detours on the project website.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]