Replace the Central Avenue Bridge to accommodate additional auxiliary lanes on the GSP
Utility upgrades
CONSTRUCTION:
Bridge construction work to be performed in three (3) stages following utility relocations
Temporary traffic shifts will be utilized to facilitate the work
Short duration temporary detours will be needed during utility relocation work
Significant utility relocation work including drainage, water mains, gas mains and electrical facilities will be performed
Utility relocation work to begin on or about November 2018
Location Updates
November 26, 2021
Central Avenue traffic has been restored to its original configuration and all work zones removed. All travel lanes and turn lanes have been re-opened over the bridge. Eastbound and westbound left turns at Oraton Parkway and Whittlesey Avenue are restored.
No work planned.
October 29, 2021
Central Avenue traffic has been restored to its original configuration and all work zones removed. All travel lanes and turn lanes have been re-opened over the bridge. Eastbound and westbound left turns at Oraton Parkway and Whittlesey Avenue are restored.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]