Replace the Central Avenue Bridge to accommodate additional auxiliary lanes on the GSP
Utility upgrades
CONSTRUCTION:
Bridge construction work to be performed in three (3) stages following utility relocations
Temporary traffic shifts will be utilized to facilitate the work
Short duration temporary detours will be needed during utility relocation work
Significant utility relocation work including drainage, water mains, gas mains and electrical facilities will be performed
Utility relocation work to begin on or about November 2018
Location Updates
August 10, 2018
During the week of 08/27/18, utility-related work will be performed on Oraton Parkway at Central Avenue. Minor traffic impacts are expected.  Work will be supported by East Orange Police.
August 3, 2018
During the week of 08/27/18, utility-related work will be performed on Oraton Parkway at Central Avenue. Minor traffic impacts are expected.  Work will be supported by East Orange Police.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]