Location Highlights

STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)

IMPROVEMENTS:

  • Reconstruction of deck, sidewalks, railings/parapets and lighting
  • Roadway milling and resurfacing of East Passaic Avenue at both approaches
  • Guide rail, curb, sidewalk, fencing and traffic striping on East Passaic Avenue

CONSTRUCTION:

  • Construction work to be performed in four (4) stages
  • Temporary traffic shifts will be utilized to facilitate the work
  • Work to begin on or about Summer 2019

Location Updates

November 20, 2020

  • During the week of 11/23/20, general clean-up and restoration work will be performed on East Passaic Avenue over the Garden State Parkway.

November 13, 2020

  • During the week of 11/16/20, guide rail installation will be performed on East Passaic Avenue over the Garden State Parkway. Work will be supported by Nutley Police as necessary.