8. STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)
Home / Project Overview / 8. STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)
Location Highlights
STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)
IMPROVEMENTS:
Reconstruction of deck, sidewalks, railings/parapets and lighting
Roadway milling and resurfacing of East Passaic Avenue at both approaches
Guide rail, curb, sidewalk, fencing and traffic striping on East Passaic Avenue
CONSTRUCTION:
Construction work to be performed in four (4) stages
Temporary traffic shifts will be utilized to facilitate the work
Work to begin on or about Summer 2019
Location Updates
November 6, 2020
During the week of 11/09/20, final pavement striping will be performed on East Passaic Avenue over the Garden State Parkway. Work will be supported by Nutley Police as necessary.
October 30, 2020
During the week of 11/02/20 through 11/09/20, roadway curb, sidewalk and guide rail construction will be performed on East Passaic Avenue over the Garden State Parkway. Work will be supported by Nutley Police as necessary.
During the week of 11/09/20, paving work will be performed on East Passaic Avenue between Harrison Street and Milton Avenue. Temporary detours of traffic will be utilized for this work. Work will be supported by Nutley Police as necessary.
The traffic alerts page will have a running list of traffic alerts throughout the duration of the Garden State Parkway Interchange 145 (Central Avenue Bridge […]