8. STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)
Home / Project Overview / 8. STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)
Location Highlights
STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)
IMPROVEMENTS:
Reconstruction of deck, sidewalks, railings/parapets and lighting
Roadway milling and resurfacing of East Passaic Avenue at both approaches
Guide rail, curb, sidewalk, fencing and traffic striping on East Passaic Avenue
CONSTRUCTION:
Construction work to be performed in four (4) stages
Temporary traffic shifts will be utilized to facilitate the work
Work to begin on or about Summer 2019
Location Updates
August 7, 2020
A new work zone has been created on the north side of East Passaic Avenue between Harrison Street and Milton Avenue for bridge demolition and construction work. Work will be supported by Nutley Police as necessary.
The pedestrian walkway over the East Passaic Avenue Bridge has been relocated to the south side of the structure.
During the weeks of 08/10/20 through 08/24/20, bridge deck reconstruction work will continue on the north side of the bridge.
July 31, 2020
A new work zone has been created on the north side of East Passaic Avenue between Harrison Street and Milton Avenue for bridge demolition and construction work. Work will be supported by Nutley Police as necessary.
The pedestrian walkway over the East Passaic Avenue Bridge has been relocated to the south side of the structure.
During the weeks of 08/03/20 through 08/17/20, bridge deck reconstruction work will continue on the north side of the bridge.
The traffic alerts page will have a running list of traffic alerts throughout the duration of the Garden State Parkway Interchange 145 (Central Avenue Bridge […]