Location Highlights

STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)

IMPROVEMENTS:

  • Reconstruction of deck, sidewalks, railings/parapets and lighting
  • Roadway milling and resurfacing of East Passaic Avenue at both approaches
  • Guide rail, curb, sidewalk, fencing and traffic striping on East Passaic Avenue

CONSTRUCTION:

  • Construction work to be performed in four (4) stages
  • Temporary traffic shifts will be utilized to facilitate the work
  • Work to begin on or about Summer 2019

Location Updates

July 26, 2019

  • During the weeks of 07/29/19 through 08/05/19, nighttime lane closures will be performed on the GSP at East Passaic Avenue for bridge related work. This work will be supported by State Police.

July 19, 2019

  • During the weeks of 07/22/19 through 08/05/19, nighttime lane closures will be performed on the GSP at East Passaic Avenue for bridge related work. This work will be supported by State Police.