Provide a two-lane entrance ramp from the Interchange 145 Toll Plaza to GSP Southbound
Widen GSP northbound to re‐establish a two-lane deceleration lane to the Interchange 145 Toll Plaza
Remove exiting Toll Plaza at Interchange 145
Minimize construction impacts on both the GSP and the local roadway network
Complete all work on the GSP within the existing right‐of‐way
CONSTRUCTION:
Construction work to be performed in three (3) stages
Temporary traffic shifts within the Toll Plaza will be utilized to facilitate the work
Work to begin on or about July 16, 2018
Location Updates
February 25, 2022
The Garden State Parkway implemented "One-Way Tolling" at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
A new work zone has been created on the left side of Interchange 145 entrance ramp to southbound Garden State Parkway, including the southbound Garden State Parkway right side at Milepost 146.7 for retaining wall construction.
Northbound Garden State Parkway traffic has been restored to its original alignment with three (3) through lanes, between Milepost 145.9 and Milepost 146.8 (Interchange 145) in East Orange and the addition of a second exit lane into Interchange 145.
During the weeks of 02/28/22 through 03/28/22, retaining wall construction work will continue within dedicated work zones along the Interchange 145 southbound entrance ramp. Traffic impacts are not anticipated.
During the week of 03/28/21, nighttime lane closures will be implemented on southbound Garden State Parkway near Interchange 145 in support of entrance ramp construction work.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]