Provide a two-lane entrance ramp from the Interchange 145 Toll Plaza to GSP Southbound
Widen GSP northbound to re‐establish a two-lane deceleration lane to the Interchange 145 Toll Plaza
Remove exiting Toll Plaza at Interchange 145
Minimize construction impacts on both the GSP and the local roadway network
Complete all work on the GSP within the existing right‐of‐way
CONSTRUCTION:
Construction work to be performed in three (3) stages
Temporary traffic shifts within the Toll Plaza will be utilized to facilitate the work
Work to begin on or about July 16, 2018
Location Updates
July 12, 2019
The Garden State Parkway implemented "One-Way Tolling" at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
Work zones have been created on the right shoulder of northbound and southbound GSP immediately south of Interchange 145 (milepost 146.5) for Central Avenue Bridge reconstruction.
A temporary exit ramp has been opened from southbound Garden State Parkway to Oraton Parkway at New Street in East Orange. The temporary exit ramp provides access to Central Avenue (CR 508) and to Newark via a detour east during bridge construction at Central Avenue. Access to Route 280 remains unchanged. Please refer to the graphic below or CLICK HERE to see full-sized, animated graphics of the detours on the project website.
During the week of 07/15/19 through 07/22/19, nighttime lane closures will be utilized in the vicinity of Central Avenue for bridge related work. Work will be supported by State Police.
During the week of 07/22/19, daytime single toll lane closures at the Interchange 145 entrance plaza will be utilized for toll booth and canopy electrical work. Minor traffic impacts are expected. Work will be supported by State Police.
July 5, 2019
The Garden State Parkway implemented "One-Way Tolling" at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
Work zones have been created on the right shoulder of northbound and southbound GSP immediately south of Interchange 145 (milepost 146.5) for Central Avenue Bridge reconstruction.
A temporary exit ramp has been opened from southbound Garden State Parkway to Oraton Parkway at New Street in East Orange. The temporary exit ramp provides access to Central Avenue (CR 508) and to Newark via a detour east during bridge construction at Central Avenue. Access to Route 280 remains unchanged. Please refer to the graphic below or CLICK HERE to see full-sized, animated graphics of the detours on the project website.
During the weeks of 07/08/19 through 07/15/19, nighttime asphalt paving operations will continue on the Garden State Parkway between mileposts 146 and 149. Nighttime lane closures will be utilized to facilitate this work. Work will be supported by State Police.
During the week of 07/08/19, daytime single toll lane closures at the Interchange 145 entrance plaza will be utilized for toll booth and canopy electrical work. Minor traffic impacts are expected. Work will be supported by State Police.
During the evenings of 07/10/19 and 07/11/19, the southbound GSP exit ramp to Route 280 at Exit 145 will close overnight and reopen in the morning for roadway lighting work. Work will be supported by State Police.
During the week of 07/22/19, daytime single toll lane closures at the Interchange 145 entrance plaza will be utilized for toll booth and canopy electrical work. Minor traffic impacts are expected. Work will be supported by State Police.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]