Provide a two-lane entrance ramp from the Interchange 145 Toll Plaza to GSP Southbound
Widen GSP northbound to re‐establish a two-lane deceleration lane to the Interchange 145 Toll Plaza
Remove exiting Toll Plaza at Interchange 145
Minimize construction impacts on both the GSP and the local roadway network
Complete all work on the GSP within the existing right‐of‐way
CONSTRUCTION:
Construction work to be performed in three (3) stages
Temporary traffic shifts within the Toll Plaza will be utilized to facilitate the work
Work to begin on or about July 16, 2018
Location Updates
November 16, 2018
The Garden State Parkway implemented "One-Way Tolling" at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
A new work zone has been created on the right shoulder of northbound GSP immediately south of Interchange 145 (milepost 146.5).
A new temporary exit ramp has been opened from southbound Garden State Parkway to Oraton Parkway at New Street in East Orange. The new temporary exit ramp provides access to Central Avenue (CR 508) and to Newark via a detour east during bridge construction at Central Avenue. Please refer to the graphic below or CLICK HERE to see full-sized, animated graphics of the detours on the project website.
During the week of 11/26/18, southbound GSP roadway travel lanes will be shifted towards the median and a work zone will be created on the right shoulder immediately south of Interchange 145 (milepost 146.5). This work will be supported by State Police.
November 9, 2018
The Garden State Parkway implemented "One-Way Tolling" at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
During the week of 11/12/18, a new work zone will be created on the right shoulder of northbound GSP immediately south of Interchange 145 (milepost 146.5). This work will be supported by State Police.
On Sunday evening, 11/11/18, a new temporary exit ramp will open from southbound Garden State Parkway to Oraton Parkway at New Street in East Orange. The new temporary exit ramp will provide access to Central Avenue (CR 508) and to Newark via a detour east during bridge construction at Central Avenue. Please refer to the graphic below or CLICK HERE to see full-sized, animated graphics of the detours on the project website.
During the week of 11/26/18, southbound GSP roadway travel lanes will be shifted towards the median and a work zone will be created on the right shoulder immediately south of Interchange 145 (milepost 146.5). This work will be supported by State Police.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]