Location Highlights

STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET

IMPROVEMENTS:

  • Reconstruction of deck, sidewalks, parapets and lighting
  • Roadway milling and resurfacing of Montgomery Street at both bridge approaches
  • Sidewalk, curb, handicap ramp and traffic striping of Montgomery Street

CONSTRUCTION:

  • Construction work to be performed in three (3) stages
  • Temporary traffic shifts will be utilized to facilitate the work
  • Work to begin on or about January 2019

Location Updates

October 11, 2019

  • Northbound Garden State Parkway has been shifted right (to the outside) at Montgomery Street, Milepost 149.7, and a work zone created in the median for bridge related work.

  • During the week of 10/14/19, nighttime lane closures will be performed on southbound Garden State Parkway near Montgomery Street, Milepost 149.7, for bridge related work. Work will be supported by State Police.

October 4, 2019

  • Northbound Garden State Parkway has been shifted right at Montgomery Street, Milepost 149.7, and a work zone created on the left for bridge related work.
  • During the week of 10/04/19, nighttime lane closures will be performed on southbound Garden State Parkway near Montgomery Street, Milepost 149.7, for bridge related work. Work will be supported by State Police.