Location Highlights

STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET

IMPROVEMENTS:

  • Reconstruction of deck, sidewalks, parapets and lighting
  • Roadway milling and resurfacing of Montgomery Street at both bridge approaches
  • Sidewalk, curb, handicap ramp and traffic striping of Montgomery Street

CONSTRUCTION:

  • Construction work to be performed in three (3) stages
  • Temporary traffic shifts will be utilized to facilitate the work
  • Work to begin on or about January 2019

Location Updates

September 13, 2019

  • Montgomery Street was restored to two-way traffic on 09/06/19.
  • Northbound Garden State Parkway has been shifted right at Montgomery Street, Milepost 149.7, and a work zone created on the left for bridge related work.

1

56
57
58
59
60

92

Project Updates

Traffic Alerts

Translate »