Reconstruction of deck, sidewalks, parapets and lighting
Roadway milling and resurfacing of Montgomery Street at both bridge approaches
Sidewalk, curb, handicap ramp and traffic striping of Montgomery Street
CONSTRUCTION:
Construction work to be performed in three (3) stages
Temporary traffic shifts will be utilized to facilitate the work
Work to begin on or about January 2019
Location Updates
June 21, 2019
Westbound Montgomery Street at JFK Drive North has been detoured to Liberty Street to accommodate bridge deck reconstruction on the bridge over the Garden State Parkway. This traffic configuration will be in place through November 2019. Work will be supported by Bloomfield Police.
During the weeks of 06/24/19 through 07/01/19, bridge deck demolition will be performed within the south side work zone. Work will be supported by Bloomfield Police.
June 14, 2019
Westbound Montgomery Street at JFK Drive North has been detoured to Liberty Street to accommodate bridge deck reconstruction on the bridge over the Garden State Parkway. This traffic configuration will be in place through November 2019. Work will be supported by Bloomfield Police.
During the week of 06/17/19 through 06/24/19, bridge deck demolition will be performed within the south side work zone. Work will be supported by Bloomfield Police.
On Tuesday, 05/28/19, a new work zone will be created on the south side of the Montgomery Street Bridge over the GSP. The current traffic detours will […]