Reconstruction of deck, sidewalks, parapets and lighting
Roadway milling and resurfacing of Montgomery Street at both bridge approaches
Sidewalk, curb, handicap ramp and traffic striping of Montgomery Street
CONSTRUCTION:
Construction work to be performed in three (3) stages
Temporary traffic shifts will be utilized to facilitate the work
Work to begin on or about January 2019
Location Updates
May 17, 2019
Westbound Montgomery Street at JFK Drive North has been detoured to Liberty Street to accommodate bridge deck reconstruction on the bridge over the Garden State Parkway. This traffic configuration will be in place through November 2019. Work will be supported by Bloomfield Police.
On Tuesday, 05/28/19, the bridge work zone will be switched from the north side to the south side of Montgomery Street. The current traffic flow configuration will remain the same. Please refer to the new graphic below and CLICK HERE to see full-sized, animated graphics of the detours on the project website. Work will be supported by Bloomfield Police.
May 10, 2019
Westbound Montgomery Street at JFK Drive North has been detoured to Liberty Street to accommodate bridge deck reconstruction on the bridge over the Garden State Parkway. This traffic configuration will be in place through November 2019. Work will be supported by Bloomfield Police.
On Monday, 05/20/19, the bridge work zone will be switched from the north side to the south side of Montgomery Street. The current traffic flow configuration will remain the same. Please refer to the new graphic below and CLICK HERE to see full-sized, animated graphics of the detours on the project website. Work will be supported by Bloomfield Police.
On Tuesday, 05/28/19, a new work zone will be created on the south side of the Montgomery Street Bridge over the GSP. The current traffic detours will […]