Reconstruct the pavement along Oraton Parkway Northbound and Southbound from Central Avenue to Park Street.
Replace five traffic signals located at the following intersections: Oraton Parkway NB with Freeway Drive; Oraton Parkway SB with Freeway Drive; Oraton Parkway NB with Williams Street; Oraton Parkway SB with Williams Street; and Oraton Parkway NB with New Street.
CONSTRUCTION:
Construction work to be performed in multiple stages between Park Avenue and immediately south of Central Avenue
Temporary traffic shifts will be utilized to facilitate the work
A temporary exit ramp from southbound Garden State Parkway to southbound North Oraton Parkway will be located south of New Street
Temporary detours will be utilized to facilitate the work
Temporary pavement repairs will be performed
Work to begin on or about July 9, 2018
Location Updates
February 26, 2021
During the week of 03/01/21, roadway reconstruction work will be performed on southbound South Oraton Parkway near Central Avenue. Work will be supported by East Orange Police.
During the weeks of 03/08/21 and 03/15/21, roadway reconstruction work will be performed on southbound Oraton Parkway between New Street and Freeway Drive.  Work will be supported by East Orange Police.
February 19, 2021
During the week of 02/22/21, roadway reconstruction work will be performed on northbound and southbound South Oraton Parkway near Central Avenue. Work will be supported by East Orange Police.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]