Location Highlights

IMPROVEMENTS:

  • Reconstruct the pavement along Oraton Parkway Northbound and Southbound from Central Avenue to Park Street.
  • Replace five traffic signals located at the following intersections: Oraton Parkway NB with Freeway Drive; Oraton Parkway SB with Freeway Drive; Oraton Parkway NB with Williams Street; Oraton Parkway SB with Williams Street; and Oraton Parkway NB with New Street.

CONSTRUCTION:

  • Construction work to be performed in multiple stages between Park Avenue and immediately south of Central Avenue
  • Temporary traffic shifts will be utilized to facilitate the work
  • A temporary exit ramp from southbound Garden State Parkway to southbound North Oraton Parkway will be located south of New Street
  • Temporary detours will be utilized to facilitate the work
  • Temporary pavement repairs will be performed
  • Work to begin on or about July 9, 2018

Location Updates

June 19, 2020

  • Retaining wall reconstruction work will continue along South Oraton Parkway northbound.

 

June 12, 2020

  • During the week of 06/15/20, periodic daytime closures of South Oraton Parkway northbound at Central Avenue will be implemented, 8:00AM to 4:00PM. Daytime street parking will be temporarily restricted. Local access will be maintained via Winthrop Terrace. Work will be supported by East Orange Police.

 