Reconstruct the pavement along Oraton Parkway Northbound and Southbound from Central Avenue to Park Street.
Replace five traffic signals located at the following intersections: Oraton Parkway NB with Freeway Drive; Oraton Parkway SB with Freeway Drive; Oraton Parkway NB with Williams Street; Oraton Parkway SB with Williams Street; and Oraton Parkway NB with New Street.
CONSTRUCTION:
Construction work to be performed in multiple stages between Park Avenue and immediately south of Central Avenue
Temporary traffic shifts will be utilized to facilitate the work
A temporary exit ramp from southbound Garden State Parkway to southbound North Oraton Parkway will be located south of New Street
Temporary detours will be utilized to facilitate the work
Temporary pavement repairs will be performed
Work to begin on or about July 9, 2018
Location Updates
May 1, 2020
During the weeks of 05/04/20 and 05/11/20, sidewalk and curb reconstruction work will be performed on Whittlesey Avenue. Please refer to the graphic below for details. Work will be supported by East Orange Police.
During the weeks of 05/04/20 through 05/18/20, periodic daytime closures of South Oraton Parkway northbound at Central Avenue will be implemented, 8:00AM to 4:00PM. Daytime street parking will be temporarily restricted. Local access will be maintained via Winthrop Terrace. Work will be supported by East Orange Police.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]