Location Highlights

IMPROVEMENTS:

  • Reconstruct the pavement along Oraton Parkway Northbound and Southbound from Central Avenue to Park Street.
  • Replace five traffic signals located at the following intersections: Oraton Parkway NB with Freeway Drive; Oraton Parkway SB with Freeway Drive; Oraton Parkway NB with Williams Street; Oraton Parkway SB with Williams Street; and Oraton Parkway NB with New Street.

CONSTRUCTION:

  • Construction work to be performed in multiple stages between Park Avenue and immediately south of Central Avenue
  • Temporary traffic shifts will be utilized to facilitate the work
  • A temporary exit ramp from southbound Garden State Parkway to southbound North Oraton Parkway will be located south of New Street
  • Temporary detours will be utilized to facilitate the work
  • Temporary pavement repairs will be performed
  • Work to begin on or about July 9, 2018

Location Updates

November 26, 2021

  • During the weeks of 11/29/21 and 12/06/21, tree planting will be performed along Oraton Parkway between Central Avenue and Park Avenue. “No Parking” signs will be posted daily along impacted areas and the work will be supported by East Orange Police.

 

October 29, 2021

  • No work planned.

 


1

3
4
5
6
7

92

Project Updates

Traffic Alerts

Advisory: May 14, 2019

Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]