Reconstruct the pavement along Oraton Parkway Northbound and Southbound from Central Avenue to Park Street.
Replace five traffic signals located at the following intersections: Oraton Parkway NB with Freeway Drive; Oraton Parkway SB with Freeway Drive; Oraton Parkway NB with Williams Street; Oraton Parkway SB with Williams Street; and Oraton Parkway NB with New Street.
CONSTRUCTION:
Construction work to be performed in multiple stages between Park Avenue and immediately south of Central Avenue
Temporary traffic shifts will be utilized to facilitate the work
A temporary exit ramp from southbound Garden State Parkway to southbound North Oraton Parkway will be located south of New Street
Temporary detours will be utilized to facilitate the work
Temporary pavement repairs will be performed
Work to begin on or about July 9, 2018
Location Updates
April 19, 2019
A new work zone and traffic pattern has been established on westbound Freeway Drive over the GSP. This work zone will be utilized for traffic signal construction.
Continue roadway reconstruction work at the intersection of Freeway Drive and southbound Oraton Parkway. Work will be supported by East Orange Police.
Continue new roadway lighting installation between Central Avenue and Freeway Drive. Work will be supported by East Orange Police.
April 12, 2019
A new work zone and traffic pattern has been established on westbound Freeway Drive over the GSP. This work zone will be utilized for traffic signal construction.
Continue roadway reconstruction work at the intersection of Freeway Drive and southbound Oraton Parkway. Work will be supported by East Orange Police.
Continue new roadway lighting installation between Central Avenue and Freeway Drive.
Starting the week of 05/13/19 and continuing through 06/24/19, new roadway curb, sidewalk and driveway aprons will be constructed along Oraton Parkway northbound and southbound […]