Location Highlights

IMPROVEMENTS:

  • Reconstruct the pavement along Oraton Parkway Northbound and Southbound from Central Avenue to Park Street.
  • Replace five traffic signals located at the following intersections: Oraton Parkway NB with Freeway Drive; Oraton Parkway SB with Freeway Drive; Oraton Parkway NB with Williams Street; Oraton Parkway SB with Williams Street; and Oraton Parkway NB with New Street.

CONSTRUCTION:

  • Construction work to be performed in multiple stages between Park Avenue and immediately south of Central Avenue
  • Temporary traffic shifts will be utilized to facilitate the work
  • A temporary exit ramp from southbound Garden State Parkway to southbound North Oraton Parkway will be located south of New Street
  • Temporary detours will be utilized to facilitate the work
  • Temporary pavement repairs will be performed
  • Work to begin on or about July 9, 2018

Location Updates

September 21, 2018

  • A new work zone has been established on southbound Oraton Parkway between Williams Street and Freeway Drive to facilitate roadway reconstruction.  Street parking is temporarily eliminated is this area.
  • A new work zone and traffic pattern has been established on westbound Freeway Drive over the GSP. This work zone will be utilized for traffic signal construction.
  • Roadway reconstruction work will continue at the intersection of Freeway Drive and southbound Oraton Parkway. Work will be supported by East Orange Police.
  • Continue roadway reconstruction work at the intersection of Freeway Drive and southbound Oraton Parkway.
  • Continue roadway reconstruction work at the intersection of Freeway Drive and northbound Oraton Parkway.
  • Continue roadway reconstruction work at the intersection of New Street and northbound Oraton Parkway.
  • During the week of 09/24/18, roadway reconstruction work will begin at the intersection of Williams Street and northbound Oraton Parkway. Work will be supported by East Orange Police.
  • During the week of 10/01/18, roadway reconstruction work will begin at the intersection of Williams Street and southbound Oraton Parkway. Work will be supported by East Orange Police.

September 14, 2018

  • A new work zone has been established on southbound Oraton Parkway between Williams Street and Freeway Drive to facilitate roadway reconstruction.  Street parking is temporarily eliminated is this area.
  • A new work zone and traffic pattern has been established on westbound Freeway Drive over the GSP. This work zone will be utilized for traffic signal construction.
  • Roadway reconstruction work will continue at the intersection of Freeway Drive and southbound Oraton Parkway. Work will be supported by East Orange Police.
  • During the week of 09/17/18, roadway reconstruction work will begin at the intersection of New Street and northbound Oraton Parkway.
  • During the week of 09/24/18, roadway reconstruction work will begin at the intersection of Williams Street and northbound Oraton Parkway. Work will be supported by East Orange Police.