Project Update: June 25, 2021
PLEASE NOTE: Project updates are distributed monthly, on the last Friday of the month.
The next update will be sent out on July 30, 2021.
The following work is scheduled over the next FOUR weeks:
PLEASE NOTE: Project updates are distributed monthly, on the last Friday of the month.
The next update will be sent out on July 30, 2021.
The following work is scheduled over the next FOUR weeks:
GSP ROADWAY AND INTERCHANGE 145 TOLL PLAZA
REPLACEMENT OF CENTRAL AVENUE OVERPASS
ORATON PARKWAY IMPROVEMENTS
STRUCTURE NO. 144.7: GSP UNDER CLINTON AND SPRINGFIELD AVENUES
STRUCTURE NO. 146.0: GSP OVER 14TH AVENUE
STRUCTURE NO. 146.1: GSP OVER SOUTH ORANGE AVENUE
STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET
No work planned.
STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)