The following work is scheduled over the next three weeks:

GSP ROADWAY AND INTERCHANGE 145 TOLL PLAZA

  • The Garden State Parkway implemented “One-Way Tolling” at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.

  • Exiting Toll Plaza reconstruction continues.

  • During the week of 09/10/18, roadway paving work will be performed within the exiting toll plaza area. This work will be supported by State Police.

 

REPLACEMENT OF CENTRAL AVENUE OVERPASS

  • Utility-related work will continue on Oraton Parkway at Central Avenue. Work will be supported by East Orange Police.

ORATON PARKWAY IMPROVEMENTS

  • Roadway reconstruction work will continue at the intersection of Freeway Drive and southbound Oraton Parkway. Work will be supported by East Orange Police.
  • During the week of 08/27/18, a utility excavation will be performed on northbound Oraton Parkway at Williams Street. Work will be supported by East Orange Police.

STRUCTURE NO. 144.7: GSP UNDER CLINTON AND SPRINGFIELD AVENUES

  • No work planned.

STRUCTURE NO. 146.0: GSP OVER 14TH AVENUE

  • No work planned.

STRUCTURE NO. 146.1: GSP OVER SOUTH ORANGE AVENUE

  • No work planned.

STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET

  • No work planned.

STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)

  • No work planned.