Weekly Project Update: August 3, 2018
The following work is scheduled over the next three weeks:
The following work is scheduled over the next three weeks:
GSP ROADWAY AND INTERCHANGE 145 TOLL PLAZA
The Garden State Parkway implemented “One-Way Tolling” at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
During the evening of 08/06/18, asphalt paving work will be performed in the northbound GSP exit Toll Plaza. Traffic impacts are expected. This work will be supported by State Police.
During the evening of 08/07/18, traffic exiting the northbound GSP at Interchange 145 will be shifted to the right of the plaza into a new traffic pattern to accommodate Toll Booth removal work and plaza pavement reconstruction. This work will be supported by State Police.
REPLACEMENT OF CENTRAL AVENUE OVERPASS
ORATON PARKWAY IMPROVEMENTS
STRUCTURE NO. 144.7: GSP UNDER CLINTON AND SPRINGFIELD AVENUES
STRUCTURE NO. 146.0: GSP OVER 14TH AVENUE
STRUCTURE NO. 146.1: GSP OVER SOUTH ORANGE AVENUE
STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET
STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)