Weekly Project Update: October 5, 2018
The following work is scheduled over the next three weeks:
The following work is scheduled over the next three weeks:
GSP ROADWAY AND INTERCHANGE 145 TOLL PLAZA
The Garden State Parkway implemented “One-Way Tolling” at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
Perform work area cleanup within the Interchange 145 (Exit) Toll Plaza. This work will be supported by State Police.
During the week of 10/29/18, northbound GSP roadway travel lanes will be shifted towards the median and a work zone will be created on the right shoulder immediately south of Interchange 145 (milepost 146.5). This work will be supported by State Police.
REPLACEMENT OF CENTRAL AVENUE OVERPASS
ORATON PARKWAY IMPROVEMENTS
STRUCTURE NO. 144.7: GSP UNDER CLINTON AND SPRINGFIELD AVENUES
STRUCTURE NO. 146.0: GSP OVER 14TH AVENUE
STRUCTURE NO. 146.1: GSP OVER SOUTH ORANGE AVENUE
STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET
STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)