Weekly Project Update: September 21, 2018

 In Project Updates

The following work is scheduled over the next three weeks:

GSP ROADWAY AND INTERCHANGE 145 TOLL PLAZA

  • The Garden State Parkway implemented “One-Way Tolling” at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.

  • During the week of 09/24/18, southbound GSP roadway travel lanes will be shifted towards the median and a work zone will be created on the right shoulder immediately north of Interchange 145 (milepost 147.5). This work will be supported by State Police.

  • During the week of 10/08/18, northbound GSP roadway travel lanes will be shifted towards the median and a work zone will be created on the right shoulder immediately south of Interchange 145 (milepost 146.5). This work will be supported by State Police.

REPLACEMENT OF CENTRAL AVENUE OVERPASS

  • Utility-related work will continue on Oraton Parkway at Central Avenue near Oraton Parkway and Birchwood Avenue. Work will be supported by East Orange Police.

ORATON PARKWAY IMPROVEMENTS

  • A new work zone has been established on southbound Oraton Parkway between Williams Street and Freeway Drive to facilitate roadway reconstruction.  Street parking is temporarily eliminated is this area.
  • A new work zone and traffic pattern has been established on westbound Freeway Drive over the GSP. This work zone will be utilized for traffic signal construction.
  • Roadway reconstruction work will continue at the intersection of Freeway Drive and southbound Oraton Parkway. Work will be supported by East Orange Police.
  • Continue roadway reconstruction work at the intersection of Freeway Drive and southbound Oraton Parkway.
  • Continue roadway reconstruction work at the intersection of Freeway Drive and northbound Oraton Parkway.
  • Continue roadway reconstruction work at the intersection of New Street and northbound Oraton Parkway.
  • During the week of 09/24/18, roadway reconstruction work will begin at the intersection of Williams Street and northbound Oraton Parkway. Work will be supported by East Orange Police.
  • During the week of 10/01/18, roadway reconstruction work will begin at the intersection of Williams Street and southbound Oraton Parkway. Work will be supported by East Orange Police.

STRUCTURE NO. 144.7: GSP UNDER CLINTON AND SPRINGFIELD AVENUES

  • No work planned.

STRUCTURE NO. 146.0: GSP OVER 14TH AVENUE

  • No work planned.

STRUCTURE NO. 146.1: GSP OVER SOUTH ORANGE AVENUE

  • No work planned.

STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET

  • No work planned.

STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)

  • No work planned.